Alrosa Working on New Diamond Mine
December 25, 12Sorter at an Alrosa diamond sorting center |
The Russian diamond-mining giant started to strip overburden at the Botuobinskaya, the first phase in developing the deposit. The stripping operations will last for three years.
The diamond pipe will be mined as an open pit and its ore will be processed at Nyurba. Botuobinskaya is located within the Nakyn Ore Field, 3 kilometer from the Nyurbinskaya diamond pipe.
The mine has a high grade of 5.13 carats per tonne, and a diamond reserve exceeding 70 million carats, Alrosa reported.
A high proportion of gem-quality and near-gem-quality stones with a high degree of transparency characterizes the Botuobinskaya diamonds, according to the release.